|
Thematic Area: Social
and Cultural
EU Programme: LEADER (and
Irish National Development Plan)
Name of the project: Seanscoil
an Chrompáin
Lead institution/Consortium
of partners: Comhlacht Forbartha Áitiúil
Acla (CFA)(Achill Local Development Company) &
Meitheal Forbartha na Gaeltachta
Introduction:
This project was undertaken by
Comhlacht Forbartha Áitiúl Acla
(CFA) in a marginalized, remote location - Achill
Island - off the north-west coast of Co. Mayo,
Ireland, where the community inherited an old
dilapidated school from the parish priest, and
plans were made to renovate the building for use
as a community centre, office space for voluntary
organisations and a crèche. Achill Island
is a breac-Ghaeltacht (semi-Irish speaking) area.
The newly refurbished community centre was to
afford a venue for Irish language and cultural
activities as well as community development projects
in general. CFA approached Meitheal Forbartha
na Gaeltachta (MFG) who administers LEADER funding
in Gaeltacht areas. With the bottom-up ethos of
MFG, local community members were guided to assume
responsibility for the project themselves, and
sought long-term ownership of the school. Once
ownership had been secured by the community, an
engineer was employed to draw up a renovation
plan. On receipt of these plans, and on the advice
of MFG, a consortium of partners evolved, on a
geographical basis, to include community, local
and state representatives; together with social
partners, so that all aspects of community life
were represented. Partners had worked separately
in the same area, but MFG specifically brought
them together on this project. Many public meetings
were undertaken in Achill for feedback on usage
of the building, and there was constant communication
between CFA and MFG staff. The project commenced,
and as the community was not allowed to knock
the old building renovations were undertaken in
various stages. The project evolved as the work
progressed, and as it did, it was necessary to
make further additions and adjustments to the
original plans.
Selection of sources of funding:
The total cost of the project
was €400,000. As there were limited funds
available through MFG, a partnership approach
was adopted, and guided by MFG who assisted the
community in approaching Mayo County Council and
the NDP CLÁR Programme (funding that covers
areas that have lost more than 50% of their population
since 1986). From initial discussions it transpired
that CLÁR were willing to equally match
LEADER funding, but the combined grant total was
not to exceed 50% of the total cost. The additional
funding had to be raised locally, and the community
felt intimidated by the thought of raising such
a large amount of money. Under the guidance of
MFG the community received €92,000 from LEADER/NRDP,
€92,000 from CLÁR and €139,000
from Mayo County Council with the balance from
the local community.
Issues:
While funding for the project
was secured, some problems arose:
1. While MFG had built similar
projects in their own individual network areas
(even pre-LEADER); and while expert opinion and
input was sought from individuals with experience
in similar renovation projects, problems were
encountered with the refurbishment of the old
schoolhouse due to the age of the building, thus
as activities progressed unforeseen and unplanned
measures were necessary.
2. Additionally as work progressed,
interested parties wanted extra alterations made
to the building, to accommodate further usage
of the premises, which MFG had to cap due to limited
finances.
3. A problem with phased payments
transpired in the process of renovations. Flexibility
was a necessary component to ensure completion
of the project, and this was one of the major
time-consuming issues that needed to be constantly
addressed. MFG did not have the same flexibility
as other invested parties and were always subject
to some bureaucratic rule or regulation that was
irrelevant and unhelpful. Of particular hindrance
was Rule 12:10 of LEADER+ Operating Rules, which
is unrealistic in that 50% of the project needed
to be completed before any phased payment could
be made. This was an almost impossible requirement
in a small rural area employing numerous small
local contractors.
Outcome:
The project commenced in June
2003, with renovations to the old schoolhouse
completed by October 2004, and the building is
currently in use by various organisations and
local community groups. The premises will be officially
opened in December 2004 by the Minister for Community,
Gaeltacht and Rural Affairs.
The successful outcome can be
attributed to the experience of MFG in handling
such projects; the perseverance of CFA and the
determination of the local committee in overcoming
all obstacles. The key stakeholders demonstrated
good local management, and consistent, effective
communication throughout the process.
Given the Gaeltacht area in question,
and the community needs to be addressed, MFG looked
at this project as a challenge; and while considering
the risks of the project, focussed more on the
benefits of community involvement in the development
process. From a social perspective, the secondary
benefits of this project, and the impact on the
community at many levels, were immeasurable.
Recommendations:
1. Funding programmes need to
be more flexible and adapt to changing circumstances
to ensure local needs are addressed.
2. Project plans should be more
flexible and allow for a change of circumstances.
Contact: Terence Dever
Seanscoil an Chrompáin
An Caol
Oiléan Acla
Co. Mhaigh Eo
Ireland
www.mfg.ie
mfgciarrai@eircom.ie
T. +353.91953410

|