|
Thematic Area: Regional
Development
EU Programme: INTERREG
IIIA Italia-Slovenia 2004-2006 (Call for proposals:
30 November 2004)
Title of the project: Sentieri
di Pace/Poti Miru
Lead institution/Consortium
of partners: Provincia di Udine, Associazione
don Eugenio Blanchini, Associazione sportiva "Saltainbici",
Click Idea Snc, Planinska Druina Bene?ije,
Associazione per il turismo equestre nel Nordest,
Comunità montana del Torre, del Natisone
e del Collio, Fogolar Viaggi Srl, Ustanova Fundacija
Poti Miru v Poso?iju.
Selection of possible EU programmes;
finding, collecting and analysing calls for proposals
This project involves developing
materials for tourism and uses two minority languages:
Slovenian in Italy and Italian in Slovenia. At
the time of writing the project is still being
implemented.
The main organization responsible for the proposal
has a person whose specific task it is to monitor
the relevant EU calls for proposals, and this
project was the first to be devised in response
to the 2004 EU Call for proposals under the Interreg
programme.
The drafters did not use all the available information
on the EU website announcing the call for proposals.
In fact, only information found on the Friuli-Venezia
Giulia Regional Governmental website was used.
They did, however, use other bibliographic sources
to reinforce the proposal.
Other sources of funding
Funding for this project came
from the following sources:
EU, 50%
Self-funding, 5%
Other sources, 45%
The fact that EU funding was obtained
did open up other sources of funding. It has been
a stimulus and a good opportunity for putting
investment proposals to private economic operators.
Partners
The consortium of partners was
set up by convening all the associations of the
territory of Valli del Natisone that are involved
in areas covered by the proposal. The following
had wide experience in working together as a group:
Provincia di Udine (Udine), Comunità montana
del Torre, del Natisone e del Collio (S. Pietro
al Natisone), Ustanova Fundacija Poti Miru v Poso?iju
(Kobarid-Slovenija). Planinska Druina Bene?ije
(San Pietro al Natisone) had some experience in
this field. Finally, for the following the experience
was new: Associazione don Eugenio Blanchini (Cividale),
Associazione sportiva "Saltainbici"
(Ronchi dei Legionari), Click Idea Snc (S. Pietro
al Natisone), Associazione per il turismo equestre
nel Nordest (Cividale del Friuli), Fogolar Viaggi
Srl (Cividale del Friuli).
Complete levels of implication, responsibility
and participation were offered to each partner.
All could contribute at all levels to the drawing
up of the proposal. The final responsibility,
obviously, belonged to the proposer, Pro Loco
Nedike Doline/Valli del Natisone.
Special channels for internal communication were
set up between partners. In particular, at joint
meetings drafting assignments of single aspects
of the projects were given to individual partners
according to their area of competence, with simultaneous
approval of all partners through consultation
using an Internet network.
To achieve a balanced, well distributed and well-equipped
team the level of participation was optimal with
the exception of the institutional partners (the
Mountain Community - an institution at district
level, between the province and the municipalities
- and the Provincial authority); they actually
played just a formal role, partly because of the
difficulty of having a delegate with propositional
and decisional powers.
Aims/purposes of the project
The idea of putting a proposal
to the EU first arose from the fact that they
had before them the problem of protecting and
promoting an historic-environmental site right
along the border.
Collecting and taking into
account experiences of other projects
The lead organisation did not
search for similar experiences which could help
to design or define the project. There was not
enough time to do so. The leading partner worked
in close contact with the "Poti Miru"
Foundation of Caporetto (another partner), and
had developed in the same period a similar "mirror
plan" to put to the Slovenian authorities.
Unfortunately the different deadlines for the
same call in Friuli-Venezia-Giulia and in Slovenia
prevented the former, in practice, from developing
a more effective combined plan. This penalized
above all the Slovenian partner, whose own project
was rejected.
The organisation did not contact those responsible
for projects which had already been funded under
earlier calls for proposals in the same programme
or budget line, and sees no need for other organisations
to take this step as being a necessary part of
the EU proposal designing procedure.
What problems/difficulties
did you have (if any) when you designed the proposal?
Analysis of stakeholders
Only a short and quick survey
was carried out to identify the potential beneficiaries
of the project: The list of local associations
was scanned to identify associations and groups
who could make a contribution to this specific
project, and those were invited.
The specific problem the drafters aimed to address
affected the following: Cultural operators interested
in the subject of the Great War, tourist operators,
environmental operators, cycle-tourist and riding
associations, institutional bodies interested
in the socio-economic development of the area,
publishing companies interested in the area of
tourism.
The impressions of the various people or organisations,
with regard to the problem or challenge, were
gathered thanks to plenary meetings and consultation
via the Internet of various drafts of the proposal
as they were developed. Direct contacts and discussions
were held, and agreements reached, to meet the
interests of the various people and organisations
involved.
Each group perceived the problem or challenge
according to its field of competence and interest.
The resources to be committed by each group to
discuss the proposal basically entailed no more
than the direct participation of some members
to meetings and consultations.
None of the stakeholders had any significant conflict
in regard to any particular strategy built into
the project, other than the relative shortage
of resources available to each partner to meet
the needs.
Analysis of the present
situation (problem tree):
The main challenge faced was the
need to safeguard and promote endangered cultural
and environmental sites in the region. There was
a need to support new economic activities in order
to halt depopulation of the mountain areas. There
was also a need to overcome the lack of institutional
coordination in economic development and in tourist
promotion policies in the Italian-Slovenian borderlands.
These problems were very clear and evident, so
no classification proved necessary nor was any
priority given.
All the same, the inclusion of Italian and Slovenian
across the border from each kin-state was not
primarily due to the fact that they are, in these
areas, lesser-used languages.
Choosing the topic
To identify the general and specific
objectives and aims, plenary meetings of the partners
offered (through brainstorming) the opportunity
of selecting the topics, which were then examined
in depth in order to state general and specific
objectives and aims.
Fortunately, the general and specific aims of
the project fitted neatly and easily into the
priorities laid down in the EU call for proposals.
No patent difficulty was found.
Setting up a team to devise
and design the proposal
The drawing up of the proposal
(the contents of which were the outcome of plenary
sessions of the partners) was drafted by a member
of the steering committee. The text was then submitted
to the partners for amendments as it was developed.
Only a few of the partners already had experience
in developing similar proposals. But no help was
requested from other organisations with experience
in European projects. Tasks were distributed among
the team members according to the specific know-how
of each partner.
Several problems were encountered in trying to
coordinate or integrate those involved in designing
the proposal, in particular two: time was short,
and the project application form was both repetitive
and too rigid.
Self-evaluation systems (ante,
ex, post)
Risk Analysis
The potential risks on the success
of the project were taken into account, and this
was mentioned in the proposal in order to leave
open further changes in the EU contract. The plan
is still in the initial implementation phase so
it is too soon to see whether the steps taken
were correct.
Working language(s)
There were problems in relation
to the working language(s) between the partners
involved at the project and for writing the proposal.
Not all the partners are bilingual (Italian-Slovenian).
There was no need, however, to resort to external
translators. The staff has enough language skills
as well as international projects experience.
Literature review/relevant
documentation selection
The documentation used for supporting
your EU proposal came from each partner's own
resources. Letters of support for the proposal
were collected from relevant institutions or experts
in the field.
Determining the work plan
and time
As already explained, the work
plan during the writing proposal process, was
decided at plenary sessions of the partners. The
respondent drafted the proposal, submitting it
to the partners for amendments while it was being
developed.
Budget issues
The EU financial statements of
the call for proposals was not read, but careful
attention was devoted to follow the EU standards
related to travel and accommodation expenses,
honoraria, fees, salaries by category and per
day, etc.
There have been no problems in relation to the
distribution of the budget by partner. The partners
decided to commit the administration of the whole
EU budget to the lead partner, so as to ensure
good coordination.
The chief problem encountered when filling in
the EU forms was that they often require detailed
evaluation, yet give limited space, so that one
can only make general statements. Nevertheless,
the proposal was completed in time.
It proved straightforward to include the European
principles and criteria (such as the multiplier
effect, dissemination of results, evaluation criteria,
European add value, European dimension, etc.)
in the proposal, for such criteria, including
quantitative ones, were specifically requested
on the project proposal form itself.
Other problems and issues/Comments
or recommendations
The deadline for Slovenia was
one month later than the Italian one. As a consequence
a joint proposal could not be presented. There
was also insufficient information and support
from the regional offices. The Slovenian proposal
was probably rejected partly on account of this
double presentation of two separate projects on
the same topic.
There are some absurd limitations in the proposal
requirements: on the face of it the aim is to
promote the economic development of a region but
at the same time remunerative economic activities
are not allowed in the project under threat of
the funding being cut off, even if the proposing
organization is a non-profit-making organisation
with extremely clear and transparent social aims
to the advantage of the local community as a whole,
as is a Pro Loco organisation.
Contact:
Roberto Pensa, member of Steering Committee
Pro Loco NEDIKE DOLINE, Valli del Natisone
Via Arengo della Slavia,1
33049 San Pietro al Natisone
e-mail: info@nediskedoline.it
Personal address:
via Brazzacco 14 I-33100 Udine
tel. 335/8420069;roberto.pensa@libero.it

|